Construction Contracts
Security Of Payments Act legislation says : On and from each reference date under a construction contract, a person: (a) who has undertaken to carry out construction work under the contract, or (b) who...
View ArticleReference Date
A reference date, in relation to a construction contract, means: (a) a date determined by or in accordance with the terms of the contract as the date on which a claim for a progress payment may be...
View ArticlePayment Claim
A person who is or who claims to be entitled to a progress payment (the claimant) may serve a payment claim on the person who, under the construction contract concerned, is or may be liable to make the...
View ArticleSecond Notice
An adjudication application to which subsection (1) (b) applies cannot be made unless: (a) the claimant has notified the respondent, within the period of 20 business days immediately following the due...
View ArticleAdjudication
A claimant may apply for adjudication of a payment claim (an adjudication application) if: (a) the respondent provides a payment schedule under Division 1 but: (i) the scheduled amount indicated in...
View Article